There is no single Texas rule for metal building permits: what you need depends on whether the lot is inside a city or in unincorporated county, and whether it touches a flood plain or needs a septic system. Under Texas Local Government Code Chapter 233, county authority is limited to unincorporated areas, and cities have their own building rules. In Gillespie County, the County Engineering Department asks for a Development Permit Determination Form before development starts. This guide shows where to check first. It is general information, not legal advice, and the county or city makes the final call.
Where to check for a metal building permit
| Question | Who to ask | What we found |
|---|---|---|
| Is the lot inside city limits? | The city permit office (for example Fredericksburg) | Inside a city, municipal rules apply; county authority is limited to unincorporated areas (Local Government Code Ch. 233) |
| Unincorporated Gillespie County | Gillespie County Engineering Department | Requires a Development Permit Determination Form (DDF) before development |
| Flood plain or drainage | County engineer or floodplain administrator | Gillespie County checks whether a project is in or within 100 ft of the special flood hazard area |
| Septic for a barndominium, shop with restroom or house | TCEQ or the county’s authorized agent | On-site sewage facilities have their own permitting and construction requirements |
| Kerr, Kendall, Blanco, Burnet, Llano, Mason counties | That county’s office | Rules not summarized here; ask before you order |
Permits for a metal building in Gillespie County
The County Engineering Department uses the Development Permit Determination Form to identify what a project needs, including whether it sits in the special flood hazard area and which permits apply. County materials also state that it must be completed before certain other permits, such as septic, can be approved. If a project is inside Fredericksburg, ask the city as well.
Barndominium and septic permits
If the building will have a bathroom, kitchen or living space and no sewer is available, a septic system is usually part of the project. The Texas Commission on Environmental Quality publishes permitting, maintenance and construction requirements for on-site sewage facilities and lists the local governments that run the program for TCEQ. Start with our barndominium page if you are planning a home.
Metal garages, shops and carports
For a metal garage or carport or a shop, the same two questions decide everything: city or county, and flood plain or not. Ask the office what drawings they want. Some ask for a site plan, and we do not publish a size cutoff because we could not source one.
The usual order of a permitted project
- Confirm the parcel location and whether it is inside city limits.
- Contact the city permit office or the county engineering office and ask what applies.
- Get the flood plain and septic answers before you finalize the building size and location.
- Submit what they require, then schedule site preparation and the foundation.
- Order and erect the building; see metal building erection.
Review times and fees vary by office, so we do not quote them. Budget questions? Read the metal building cost guide.
Soil, rock and drainage notes
Gillespie County’s form screens for flood hazard areas and impervious cover, so slope, drainage and hard surfaces matter early. Rock and slope also change pad work and cost, which is why we ask for a photo of the building area with every request.
Get a written estimate for your metal building project
Call 830-241-8226 or send the details through our contact form: the size or acreage, what it will be used for, and the nearest town.
Metal building permit questions
Do I need a permit for a metal building in Texas?
It depends on where the building is. Texas counties have limited authority over construction in unincorporated areas, and cities set their own rules inside city limits, so confirm with the county or the city before you order.
Do I need a permit for a metal garage or a 20×20 carport?
Do not assume a small size exempts you. Call the city permit office if you are inside city limits, or the county office if you are not, and ask about your exact size and use.
Do I need a permit for a barndominium?
A barndominium is a home, so plan for more than a shed. In Gillespie County the Engineering Department reviews a Development Permit Determination Form first, and a septic system is permitted separately through the on-site sewage facility program.
Does a flood plain change the requirements?
Yes. Gillespie County’s form checks whether a project is in or near the special flood hazard area, and development there must meet the county’s Flood Damage Prevention Ordinance.
Who can tell me the rules for Kerr, Kendall or Blanco County?
Each county’s own office. We have not published their rules here, so call the county or city permit office and ask what applies to your parcel.
Sources
- Texas Local Government Code Chapter 233, County Regulation of Land Use and Structures
- Gillespie County, Engineering Department (Development Permit Determination Form)
- TCEQ: On-Site Sewage Facilities (including septic systems)
Checked November 8, 2026. Rules change; confirm with your county or city before you build.